4th span of Padma Bridge mounted

National Desk, Rashedul Islam Biplob , Staff Reporter: Dhaka Office: Alltimenews.com:- 4th span of Padma Bridge mounted, Around 600 meters of tons-hyped Padma Bridge is now seen following the installation of 4th span on pillar no 40 and forty one the day prior to this, reports UNB. The span has been hooked up inside the Jajira point in the morning.

Earlier on Saturday afternoon, the span changed into added to the factor from Mawa production yard.
The work of Padma Multipurpose Bridge became visible with the installation of a a hundred and fifty-metre first span at the pillars no 37 and 38 on October 30. The production paintings at the us of a’s biggest bridge started in December in 2015. The 6.15-km bridge could have a total of forty one spans, every a hundred and fifty meters lengthy. According to the engineers worried, a complete of forty one spans will be mounted on 42 concrete pillars.

 

National Desk, Alltimenews.com